The ninth-floor slab was cast at the end of the month. Brickwork is up to the seventh floor and the lift shafts are ready for installation.
Casting of the ninth-floor slab at Tower B finished on schedule at the end of last month. That puts the structure one floor from its final height.
Where the rest of the building stands today:Structure — nine of ten floors cast; the tenth is scheduled for next month.
Brickwork — complete to the seventh floor.
Plumbing and electrical — first-fix conduit run to the fifth floor.
Lifts — both shafts complete; the supplier surveys next month.
Façade — glazing frames fitted on the north elevation up to the fourth floor.
Owners with an instalment tied to a construction milestone will see the ninth-floor slab reflected in their next statement. If you are not sure which milestone your next payment follows, your payment schedule lists it, and the accounts desk can send a copy.