Tower B Progress: Roof Casting Complete on the Ninth Floor

2 min read · Project Management Team

Tower B Progress: Roof Casting Complete on the Ninth Floor

The ninth-floor slab was cast at the end of the month. Brickwork is up to the seventh floor and the lift shafts are ready for installation.

Casting of the ninth-floor slab at Tower B finished on schedule at the end of last month. That puts the structure one floor from its final height.

Where the rest of the building stands today:Structure — nine of ten floors cast; the tenth is scheduled for next month.

Brickwork — complete to the seventh floor.

Plumbing and electrical — first-fix conduit run to the fifth floor.

Lifts — both shafts complete; the supplier surveys next month.

Façade — glazing frames fitted on the north elevation up to the fourth floor.

Owners with an instalment tied to a construction milestone will see the ninth-floor slab reflected in their next statement. If you are not sure which milestone your next payment follows, your payment schedule lists it, and the accounts desk can send a copy.